Construction at San Marcos High School Interim Campus Begins  

Posted: Monday, September 19, 2011

Construction on the Interim Campus, which is where students and teachers will attend classes while the new school is being built, has begun and is scheduled for completion at the end of Novermber. Teachers will then move their classrooms over the Christmas break with students attending class at the Interim Campus starting the spring semester.  Site demolition of the existing school is scheduled for January 2012.

The new facility will be a 400,000 square foot tilt up and steel school on a newly improved 1.6 million square foot site.  The approximately 2,200 students are scheduled to start classes there in 2014.